Average delay in commissioning of solar project is 17 months

New Delhi

Issues such as disruptions during land acquisition and slow pace of transmission capacity expansion are impacting the commissioning of solar power projects with delays averaging at around 17 months.

Ember in its latest report on risks associated with renewable energy expansion (RE) in India said that utility-scale RE projects in India have been mired with cases of delays due to various factors.

“Project-level data from the Central Electricity Authority (CEA) shows an average delay of 17 months (P50), with delays extending to 26 months in extreme cases (P90). In some instances, delays have reached up to 34 months, with some projects eventually being scrapped,” it said.

These delays are measured from the scheduled commercial operation date (SCOD) as specified in tender documents—typically 18 to 24 months from the date of execution of the power purchase agreements (PPAs).

Risk premiums

The Ember report evaluates risk premium for solar power projects based on two benchmarks. P50, or the average scenario, that is the most likely outcome, with a 50 per cent probability that actual results will meet or exceed this level. It is considered a balanced estimate of expected returns.

Second is P90, or the conservative scenario, which represents an outcome with a 90 per cent probability that actual results will meet or exceed this level. P90 is favoured by very risk averse investors, as it ensures preparedness for unfavourable outcomes.

Ember explained that choice between using P50 and P90 estimates reflects an investor’s risk tolerance. For instance, if historical data shows that the capacity utilisation factor (CUF) for a solar project ranges between 18 per cent and 22 per cent, a risk-averse investor might assume a CUF of 18 per cent, while a less risk-averse investor may use a more balanced estimate of 20 per cent.

The report pointed out that project delays typically arise from three reasons: land acquisition for setting up the plant, connectivity to the grid, and finalising PPAs.

Delay factors

Ember said that the land acquisition process, which is typically expected to take 6-9 months, can extend to 18-24 months in certain states, posing significant risks to maintaining SCOD timelines.

With project commissioning deadlines usually set at 18-24 months post the execution of the PPA, this process of acquiring land can be a major bottleneck, it added.

Issues such as administrative hurdles, non-digitised land records, fragmented local regulations and a lack of centralised land policies complicate project development and delay financial closure.

Besides, the process for obtaining General Network Access (GNA) or connecting to the interstate transmission system (ISTS), as estimated from typical timelines, requires 4.5-13.5 months, depending on whether network expansion or augmentation is required.

However, connection timelines remain uncertain due to challenges in expanding transmission and evacuation infrastructure, it added.

“Building transmission lines can typically take 24 to 36 months, with delays caused by right-of-way issues, natural barriers like rivers and hills, ecological constraints—most importantly the issue of Great Indian Bustard (GIB)—and complex crossings involving highways and railways. In regions like Rajasthan, where GIB-related permitting bottlenecks are prevalent, construction timelines can extend up to 48 months,” the report pointed out.

A significant amount of high voltage direct current (HVDC) transmission capacity has been planned and auctioned to facilitate the transfer of RE from these States.

“But HVDC projects take longer to commission due to its reliance on very specialised equipment, such as converter stations and thyristor valves, unlike HVAC systems that have much simpler equipment requirements,” Ember said.

The granted grid connectivity for solar, wind, and hybrid projects currently totals around 147 GW. However, this capacity is not available immediately and is expected to become operational over the next 3-5 years.

Source link

nasdaqpicks.com

Recent Posts

India forms consortium to develop ports overseas

India has set up a consortium to develop ports overseas and looks to improve competitiveness…

3 minutes ago

One Man’s Battle to Bring the Nazis to Justice — a stark lesson for our times

Unlock the Editor’s Digest for freeRoula Khalaf, Editor of the FT, selects her favourite stories…

10 minutes ago

Ekta Ka Mahakumbh – the Dawn of a New Era

The Mahakumbh has successfully concluded in the holy city of Prayagraj. A grand Mahayajna of…

12 minutes ago

Agritourism for Himachal – The Hindu BusinessLine

With a growing debt of over ₹1 lakh crore, Himachal is looking to revive its…

19 minutes ago

Re-imagining teacher education – The Hindu BusinessLine

“Give the pupils something to do, not something to learn; and the doing is of…

25 minutes ago

Help is coming in the AI copyright wars

Unlock the Editor’s Digest for freeRoula Khalaf, Editor of the FT, selects her favourite stories…

28 minutes ago